Resurfacing

Every spring, the Engineering team completes the annual asphalt street pavement condition survey. From this survey, the annual Street Resurfacing Priority List is developed based on the observed condition of the streets. The list is used as a guide for the preparation of the annual street resurfacing contract. A brief explanation of the priority system is as follows:

  • Priority 1 - Street requires resurfacing as soon as possible
  • Priority 2 - Street requires resurfacing in the next one to two years
  • Priority 3 - Street should be surveyed every year, maintenance procedures may extend time until resurfacing required, resurfacing necessary in approximately two-four years
  • Priority 4 - Street in fair condition, survey condition again in two years
  • Priority 5 - Street in good condition, survey condition again in three years

Click Image to View

2023 Map Prelim Major Road Projects

The “Type” column of the list indicates which method of resurfacing will be done. “R” indicates the method by which the existing surface is heater scarified and rejuvenated and a thin (1”– 11/4”) bituminous wearing surface is added. “M/O” denotes a method by which an optimum thickness (11/2” – 2½”) of the existing surface is milled off and a new surface of approximately equal thickness is added. “O” represents a straight overlay method where the existing surface is leveled with thin layer of bituminous material and then a 11/2” – 2” bituminous overlay is laid.

For questions please contact:

Eric Herbst, P.E.

(309)454-9744


2023 Street Resurfacing Schedule (WEATHER PERMITTING)


Street

Milling                    
Crack Cleaning
and Filling
Reflective Crack Control Fabric Longitudinal
Joint Sealant

Tack Coat          
Asphalt Paving
Binder Course
Asphalt Paving
Surface Course
E. College Ave (Blair Dr. To Young Dr.) Complete Complete Complete Complete Complete Complete Complete
Market St (Adelaide St. To Samantha St.) Complete N/A N/A Complete Complete Complete Complete
Samantha St. (Market St. To Kern St.) Complete N/A N/A Complete Complete Complete Complete
Madison St. (Division St. To Apple St.) Spring 2024 N/A N/A Spring 2024 Spring 2024 Spring 2024 Spring 2024
Apple St. (Madison St. To Main St.)  Spring 2024 N/A N/A Spring 2024 Spring 2024 Spring 2024 Spring 2024
S. University St. (Division St. To Apple St.) Spring 2024 Spring 2024 N/A Spring 2024 Spring 2024 Spring 2024 Spring 2024
W. Virginia Ave. (Center St. To Main St.) Complete N/A N/A Complete Complete Complete Complete
Aurora Way (Miles Ln. To Alden Dr.) Complete N/A N/A Complete Complete Complete Complete
Payne Place Complete N/A N/A Complete Complete Complete Complete
Park Drag Lane Complete N/A N/A Complete Complete Complete Complete
Cutter Court Complete N/A N/A Complete Complete Complete Complete
Carriage Hills Rd. (White Chapel Way To Beech St.) Complete N/A N/A Complete Complete Complete Complete
Beech St. (Phaeton Pl. To Raab Rd.) Complete Complete Complete Complete Complete Complete Complete
Stephens Drive Spring 2024 N/A N/A Spring 2024 Spring 2024 Spring 2024 Spring 2024
Maplewood Dr. (Stephens Dr. To Belt Ave.) Spring 2024 N/A N/A Spring 2024 Spring 2024 Spring 2024 Spring 2024
Boone Court Spring 2024 N/A N/A Spring 2024 Spring 2024 Spring 2024 Spring 2024
Belt Ave. (bridge SE of Maplewood Dr. To Maple Pl.) Spring 2024 N/A N/A Spring 2024 Spring 2024 Spring 2024 Spring 2024
Maple Pl. (Stephens Dr. To Maplewood Dr.) Spring 2024 N/A N/A Spring 2024 Spring 2024 Spring 2024 Spring 2024
Mark Lane  Spring 2024 N/A N/A Spring 2024 Spring 2024 Spring 2024 Spring 2024
Smith Dr. Spring 2024 N/A N/A Spring 2024 Spring 2024 Spring 2024 Spring 2024
Crescent Ln. (Maple Pl. To Jersey Ave.) Spring 2024 N/A N/A Spring 2024 Spring 2024 Spring 2024 Spring 2024
Ruston Ave. Complete N/A N/A Complete Complete Complete Complete
Orlando Ave. (Main St. to School St.) Complete N/A N/A Complete Complete Complete Complete
Miles Lane Complete N/A N/A Complete Complete Complete Complete
Gregory St. (School St. To Fell Ave.) Complete N/A N/A Complete Complete Complete Complete
N. Fell Ave. (Sycamore St. To Lincoln St.) Complete N/A N/A Complete Complete Complete Complete
Norwood Ave. (Fell Ave. To Lincoln St.) Complete N/A N/A Complete Complete Complete Complete
Dial Court Complete N/A N/A Complete Complete Complete Complete
Douglas St. (Cole St. To Oglesby Ave.) Complete N/A N/A N/A Complete Complete Complete
Lincoln Ave. (Cole St. To Oglesby Ave.) Complete N/A N/A Complete Complete Complete Complete
Oglesby Ave. (Beech St. To Lincoln Ave.) Complete N/A N/A Complete Complete Complete Complete

Please note that the dates above may change and work may be delayed due to weather.


Parallel parking on the street will be prohibited and streets will be subject to lane closures during the milling, priming, and asphalt paving operations.  Temporary No Parking signs will be posted as needed in the afternoon or early evening of the day before each operation is scheduled.  Please watch for these signs as no other notice will be provided.  On days when surface course is placed, lanes will be closed, with access to driveways and parking lots unavailable, until the new asphalt has adequately cooled, usually 1-2 hours but potentially up to 4-5 hours.  We do not anticipate lanes being closed overnight.   If you need to ensure use of your vehicle the day(s) the surface course is placed on your street, you will need to park elsewhere before 7:00 a.m.